CHECKING
COMPLIANCE INSPECTION PROCEDURE
Purpose and Applicability
- Assists Departments in maintaining compliance to federal and state regulations, campus policies and other requirements to which Missouri S&T chooses to comply.
- Covers all Missouri S&T activities defined within the scope of its Environmental Management System (EMS)
Definitions
- Compliance Inspection – An assessment of activities conducted involving federal or state regulations, campus policies or other requirements within a Department or laboratory.
- Compliance Inspectors – Personnel who perform compliance inspections. Compliance inspectors may be any of the Environmental Health and Safety (EHS) staff.
- Non-compliance – Non-fulfillment of a legal requirement. This would result in a corrective action.
- Non-conformance – Non-fulfillment of a non-legal requirement. This would result in a corrective action.
- Action request – A report which is generated from the Environmental Management System requesting correction of a non-conformance/non-compliance.
Procedure Steps & Responsibility
Action to be performed
|
Responsibility
|
- Look at the Compliance Inspection Schedule to determine when a department is due for inspection.
|
Campus Departments / Compliance Inspector
|
- Review information from previous compliance inspections for Department to be inspected.
|
Compliance Inspector
|
- Conduct the inspection using the appropriate checklists found in the Compliance Inspection Program. The Compliance Inspection Program verifies compliance / conformance to the information found in the Environmental Health and Safety Manual.
(Note: Departments will provide an escort if necessary during compliance inspections)
|
Compliance Inspector
|
- Communicate the inspection results with a Department representative and EMS Coordinator.
- If a non-compliance/non-conformance is identified during an inspection, a Department representative may immediately correct the non-compliance/non-conformance. The compliance inspection report will state no further action is required for items that are corrected immediately in the presence of the inspector.
- If the non-compliance/non-conformance cannot be corrected immediately, a corrective action will be listed on the inspection report. A Department has 10 working days to correct a non-compliance/non-conformance after which there will be a re-inspection. If items are found not corrected or other non-compliances/non-conformances are identified, the Action Procedure will be followed.
- If no non-compliances/non-conformances are identified the report is closed.
|
Campus Departments / Compliance Inspector
|
Objective Evidence
Record / Form |
Responsibility |
Location |
Retention |
Inspection Reports |
EHS Personnel |
EHS Dept. |
3 years |